Planning Commission Meeting Minutes
8 May 2007
7:00 p.m.
I. CALL MEETING TO ORDER
The meeting was called to order at 7:00 p.m. by Chairman William G. Syfert.
II. ROLL CALL
Members Present: Steve Galster, Tony Butrum, Bob
Diehl
Lawrence
Hawkins, David Okum, Tom
Vanover
and Chairman Syfert.
Others Present: Doyle H. Webster, Mayor
Jeff
Tulloch, Economic Development Director
Bill
McErlane, Building Official
Pat
Madl, Engineer
Anne
McBride, City Planner
III. MINUTES OF THE REGULAR MEETING OF 13 MARCH 2007
Mr. Galster moved to approve the Minutes and Mr. Butrum seconded the motion. By voice vote
all voted aye, and the Minutes were approved unanimously.
IV. CORRESPONDENCE
A. Report on Council
Mr. Galster reported that at the last Council meeting was the public hearing for
electronic interstate signs which was approved unanimously.
B. Board of Zoning Appeals Meeting Minutes 20 February 2007
C. Zoning Bulletin March 1, 2007
D. Zoning Bulletin March 15, 2007
E. Zoning Bulletin April 1, 2007
F. Revision to Zoning Code Electronic Highway Signs Section 153.534
V. OLD BUSINESS
VI. NEW BUSINESS
A. Approval of Development Plan for Sams Club Vestibule Renovation, 800 Kemper
Commons Circle
Nick Miller and Candice Briere approached the commission. Mr. Miller passed out the
material board, which they received this morning.
We are in agreement with the considerations of the May 4th review letter. Throughout the
country Sams Club is looking at some of the stores to give them a facelift and
Springdale is one of the sites. The exterior would consist of a new entry vestibule and
customer pickup canopy. During construction they will create a new temporary opening to
the north and left of the existing entry vestibule, tear down the old one and build a new
one.
PLANNING COMMISSION MEETING MINUTES
8 MAY 2007
PAGE TWO
VI A SAMS CLUB VESTIBULE RENOVATION 800 KEMPER COMMONS
Mr. Miller said also under consideration is the pallet storage area on the northeast
corner of the building. We are proposing a wall to provide an area that gives a
three-sided space to store the material. We also agree to have some kind of fence to
finish that enclosure. I just need some guidance as to what the commission would like.
There are also several interior finish remodels.
Mr. McErlane reported that we are asking that should Planning approve this we get
corrected owners affidavits. This property is held under one name and the building is held
under another.
The drawings are drawn in a stepwise progression based on this occurring after the
Wal-Mart development. There is a future existing conditions drawing which is the Wal-Mart
plan and they show their plan as a progression beyond that. I doubt that the schedule will
allow for Wal-Mart to complete their work before Sams starts their site work. The
end result will be the same, but we will be asking for drawings that reflect what is going
to be built at the time it is going to be built. That is reflected not only in grading and
utility plans, but also in the landscaping plan.
Ms. McBride reported that the parking spaces are required at a ratio of five per 1,000,
and they are close to that. Once Wal-Mart and Sams are expanded they will be a
little over four per thousand. Under the PUD Planning can alter that requirement. This is
located in a center with cross parking available so I feel comfortable with the 4.13.
We had required gates to be added to that pallet and bale storage area. The height will be
10 feet and the material will be stored within one foot of the top of it so it should not
be visible.
On the loading canopy, the proposed columns are steel and we have asked that they be brick
painted to match the rest of the building.
On the landscaping, a lot of the material is proposed to be relocated but they are not
sure where it will be stored while it is being relocated. Staff has come concern about the
viability of what is to be relocated and if it does not survive it will need to be
replaced in kind in terms of size and type of plant material.
From the approved 2000 landscaping plan, a lot of that plant material has died and never
been replaced or is in very poor condition and needs to be replaced. The applicant has
indicated that they are willing to do that and will work with us.
They are significantly under what they are allowed in terms of signage. They are allowed
661 s.f. and they are proposing 333 including the panel on the free standing sign.
On the lighting there is no change to what you have approved for the Wal-Mart. The
fixtures are 42 feet, and that is what they are proposing on the front of Sams. They
are not making changes to the side or to the rear and meet all the light levels.
PLANNING COMMISSION MEETING MINUTES
8 MAY 2007
PAGE THREE
VI A SAMS CLUB VESTIBULE RENOVATION 800 KEMPER COMMONS
Mr. Madl reported that they are proposing to realign the drive off Olde Commons Drive so
that the main drive aisle is further to the west to facilitate the expansion in front of
the building. From a conceptual standpoint we are okay with that but we will need more
detailed horizontal and vertical design work done. I think we can work out these details.
Storm water is to be controlled from the Wal-Mart plans. If the sequence of construction
changes, we will need some additional information, in particular as it relates to any kind
of detour required on Olde Commons Drive.
Mr. Okum said they have changed the drive aisle configuration to two-way. What is the
width of the drive aisles? Mr. McErlane reported that the standard is 24 feet, and Mr.
Madl added that they meet that standard.
Mr. Okum said currently on the south side of the building all the over storage of carts
are placed in view of everybody coming into the store. Typically we dont allow that;
will this be resolved? Mr. Miller reported that there is a new cart storage area provided
to handle that.
Mr. Okum said I want to make sure that the cart corrals will be non-covered. Mr. Miller
confirmed this.
Mr. Galster asked if the striping in front of the new vestibule would be on the roadway.
Mr. Miller answered said there will be pavement marked to meet the ADA code.
Mr. Okum moved to approve the development plan for Sams Club to include all staff
comments and recommendations. Also the cart corrals will be without covers or canopies as
indicated by the applicant. Mr. Butrum seconded the motion. All voted aye, and the
approval was granted unanimously.
B. Approval of Sign facing Princeton Pike AT&T/Cingular
Wireless, 11711 Princeton Pike
Mr. Vanover said I am a Cingular customer and if deemed necessary, I would excuse myself
from this discussion. No one had a problem with that and he will participate in the
discussion.
Jessica Peluso and Jeff Rouse of AT&T approached the commission members. Ms. Peluso
reported they want an extra sign on the exterior facing Princeton Pike due to lack of
visibility for our store when you are driving down Princeton Pike
Currently we have 36 square feet, and we are allowed to have 130 s.f. so an extra sign
would be within the allotted maximum square footage.
The building adjacent to us is Jared Jewelers and they have moved the building 10 to 12
feet closer to Princeton Pike and taken away visibility.
PLANNING COMMISSION MEETING MINUTES
8 MAY 2007
PAGE FOUR
VI B AT&T/CINGULAR WIRELESS SIGN 11711 PRINCETON PIKE
Mr. Rouse added that is my store, and I take the calls daily asking where we are located.
Since Jareds went up, it has been more challenging for customers to find my store.
Our traffic has decreased and I do believe that with signs on the back of the building, it
would make my store a lot more visible and people would have a clear idea of where my
location is.
Mr. McErlane reported that the applicant is requesting a 3-4 1/8 x 10-1
7/8 wall sign on the east side of the building. The code directs that you have to
have frontage to place a sign, and they dont have frontage on the east side of the
building, and the location is a wall of the Pro Vision space.
With the application there is an indication that there might be another sign requested and
since we dont have details so we recommend that Planning not consider that
additional sign.
We didnt get any information on any additional signs intended to be placed on the
north and west sides of the building. In the previous package, all three signs are
approximately the same size. What they are proposing for the other faces of the building
is 68 s.f. so this would take them to 102 s.f. total and they are permitted to have 127
s.f.
Most of the members were on this board in 2005 when the landlord remade a similar request
which was denied.
Ms. McBride said I have nothing to add except for the fact that it is an issue for
Planning Commission about the frontage required for signage and whether we want to be
consistent about this or not.
Mr. Galster said I continue to have a problem with the signage being attached to what is
basically another tenant space. I do understand your dilemma, and there is a Princeton
Plaza entrance sign mounted so that the southbound traffic can see it just past the
entryway that goes down between the jewelers and Pearl Vision. I am not opposed to coming
up with some kind of entrance sign that would have AT&T or something like that on it.
However, the idea of putting a sign on a space that you dont have is a fundamental
problem. I want to see you have a successful business and I wouldnt be opposed to
your getting some identification at that entrance. It wouldnt be huge but it would
let people know that this is the entrance for your establishment.
Mr. Okum said establishing this precedent would be a problem, and I would like to
reference the wing wall on the photo provided to us. I would think that wing wall being
attached to the Cingular space could possibly be an exposure they could put their name on
above that archway and they would have some exposure. It looks like their space. Mr.
Miller said it is.
Ms. McBride commented I do not know if it would do the applicant much good. My concern is
that you would be on it and miss the entryway in. I like Mr. Galsters idea of a
small ground mounted sign to give the driver enough notice to make this right turn in.
PLANNING COMMISSION MEETING MINUTES
8 MAY 2007
PAGE FIVE
VI B AT&T/CINGULAR WIRELESS SIGN 11711 PRINCETON PIKE
Mr.Okum commented that might be the answer for more than one tenant.
Mr. Gilhart owner of the center said I like the idea because you cannot look back towards
Cingular to see a sign. That sign is already there and If they were to take it and leave
it exactly as it is, I would have no problem with them changing it to a white background
with AT&T and a little logo. If the city agrees with this, I agree with it. We will
continue looking at the signage on an overall basis for the center, but in the meantime,
we did do Cingular an injustice by moving the building forward.
Mr. Galster said I think replacing the face of the sign is okay on a temporary basis. I
would like to upgrade it a little bit more but we can look at that at some future date.
This would be a short-term solution.
Mr. Syfert asked the applicant if they wished to withdraw their request. They indicated
they would and the application was withdrawn.
C. Approval of Façade Change Davids Bridal, 720Kemper
Commons Circle
Donald Kiley of K & A Architecture said I am here on behalf of Kimco Realty who owns
this property. This is a tenant shift within the center. They are relocating and are
asking for more visibility and an update on the side of the building.
We include some color photos and we are matching the split face block on the building and
adding EIFS (showed color samples),
Mr. McErlane reported that they are proposing to renovate the existing façade of the
former Shoe Carnival space and relocate their store to another space in the same
development. The existing store is 85 feet wide and approximately 10,000 square feet and
the new location will be 100 feet wide and 12,000 s.f.
The drawings indicate projecting pilasters flanking the entrance and extending the parapet
over the entrance which will be approximately 11 feet higher than it currently is. Two
different shades of gray are proposed. At this point we have no information on signs so I
would recommend we withhold any approval.
Mr. Galsteer asked if the parapet height was equal to Office Max? Mr. McErlane said they
are fairly close. Mr. Galster asked if this was consistent with the structural changes in
the center. Mr. McErlane confirmed this.
Mr. Okum said we go to Jacks and the cuts across the landscaping from the parking aisles
are a little odd. It would be better and should be worked out so they can have access ways
into the store. That landscaping needs updating anyway so it wouldnt hurt to look at
it.
PLANNING COMMISSION MEETING MINUTES
8 MAY 2007
PAGE SIX
FAÇADE CHANGE DAVIDS BRIDAL - 720 KEMPER COMMONS CIRCLE
Mr. Okum moved to approve the façade change with the color pallet and drawings as
submitted and including staff comments and recommendations. Mr. Butrum seconded the
motion. All voted aye, and the approval was granted unanimously.
D. Approval of Façade Change, BJs Restaurant, 11700 Princeton Pike
Jerry McClain of Carter Burgess of Dallas Texas approached the commission. I will try to
explain the differences between the approved elevation and what we are submitting.
We have taken away some of the EIFS pilasters and added some more slate to increase the
richness of the building. We also have taken away some of the metal panels and added
bronzed aluminum elements. It is the same principle that was approved by commission.
We added extruded aluminum light band for the evening, which is a nice soft light.
The footprint and everything else stays the same. We have tried to apply some of BJs
characteristics. Their concept is an upscale Chicago pizzeria. The price is a little less
than the Cheesecake Factory. There is a slate floor and slate roof; it is a top notch
quality restaurant with great food beer and service.
Mr. McErlane reported that the final development plan was approved on February 14, 20006
and modifications to that plan were approved on November 14, 2006.
Metal profile panels have been removed from the west side and replaced with an EIFS finish
which also includes some vertical fins about four feet on center.
The previous plan showed something similar to a rust color on the tower element and they
are proposing to expand that over their main entrance and also have it placed on the
northwest corner of their space so it runs the full height of their building.
The entrance to their space incorporates a revolving door and has a little bit of a glass
skylight over the top.
The pilasters have been changed to an EIFS with a slate veneer finish and there is some
sort of tube element. Mr. McClain reported it is conceptual right now; with the dark
material, we want to add depth and lightness. Mr. McErlane asked if it would incorporate a
light feature, and Mr. McClain said that it didnt.; there will only be a lower
sconce.
Mr. McErlane said we did have sign details under a previous submittal which totaled 174.42
s.f. There were no signs submitted with this package, although I met with the applicant
and they had details.
Mr. McClain said I had a signage package and BJs has a prototypical sign package but
it hasnt been developed for this.
PLANNING COMMISSION MEETING MINUTES
8 MAY 2007
PAGE SEVEN
VI D FAÇADE CHANGE BJS RESTAURANT 11700 PRINCETON PIKE
Mr. Madl reported that the PUD modification plan that they submitted is consistent with
previous as relates to site issues so there are no issues.
Mr. Okum moved to approve the plan as submitted including staff comments and
recommendations and the color palette as submitted. No signage will be approved at this
time. Mr. Galster seconded the motion. All voted aye, and the approval was granted
unanimously.
VII. DISCUSSION
Mr. Galster reported that Council made a minor change to the electronic sign ordinance
attachment and added a maintenance paragraph.
Mr. McErlane said I have one Zoning Code amendment I would like for Planning Commission to
at least agree on in concept even if we dont have the total language tweaked.
The draft in front of you came from the law directors office. It provides for a
progressive penalty for Zoning Code violations. Currently our penalty is a Minor
Misdemeanor and can be paid out like a traffic ticket. So when we find someone in
violation we write a complaint which may take a few days to serve, and they can come in
and pay $50 and it never gets resolved. So, we start the process over again. Particularly
if we are talking business violations, $50 is not much of a penalty to pay to be in
violation of the Zoning Code.
So if we have more than one violation in a two-year period, it will be subject to a Fourth
Degree Misdemeanor and if there are more than two guilty determinations in a two-year
period, it goes to Third Degree and if it is three convictions in a two-year period it
goes to Second Degree.
The real advantage is that once it gets to at least a Fourth Degree Misdemeanor, they have
to appear in court, and that gets their attention, particularly with corporations who have
to bring their attorneys into Mayors Court.
Mr. Okum commented it makes good sense and should be moved forward.
Mr. Galster said it doesnt have to be the same violation, right? Mr. McErlane
responded we typically would use it for the same violation although as it is worded it
could be any violation. Mr. Galster commented I think it is important for us to find a way
to get tougher on all of our maintenance and building code violations. If this allows that
to happen, I am all for it. Anything we can do to get tougher and get some of these
buildings in better shape, Ill be supporting that here and in Council as well.
Mr. Hawkins asked who would be responsible. Mr. McErlane reported we are informed by the
Police Department when they are paid out so we would have record of their previous
appearances. Mr. Hawkins wondered if it would be the owner, and Mr. McErlane answered in
most cases. In rental properties, it might be the tenant.
Mr. Vanover agreed with Mr. Galster. Its not fair to the rest of the residents and
commercial citizens who take pride in their property.
PLANNING COMMISSION MEETING MINUTES
8 MAY 2007
PAGE EIGHT
VII DISCUSSION ZONING CODE AMENDMENT PENALTIES
Mr. Galster said I know we have to give them a certain amount of time to get something
done, but if they cant cut their grass in two days, we should be cutting it. If we
need to shorten the time to address the lawn issue, I think we should. We should have the
law director look to make sure we have allowed a reasonable amount of time and have a much
more effective enforcement of the grass length; we should look at that as well.
Mr. Okum said I agree, but you have to consider a persons rights when you are
entering their property with a contractors equipment. We have to cover and protect
the Citys interests as well.
Mr. Okum moved to refer this to Council and Mr. Butrum seconded the motion. By voice vote,
all voted aye, and this will be referred to Council.
VIII. CHAIRMANS REPORT
A. King Wireless 11586 Springfield Pike Window Sign
B. Entenmanns 123 West Kemper Road Wall Sign
C. K & G Fashion Superstore 895 East Kemper Road (former Barnes & Noble)
Wall Sign and Panel Change in Pole Sign
D. Mallard Lakes 12100 Lake Circle Drive Ground Sign
E. John Brito Notario Publico 282 Northland Blvd. Wall Sign
IX. ADJOURNMENT
Mr. Vanover moved to adjourn and Mr. Butrum seconded the motion. By voice vote, all voted
aye, and Planning Commission adjourned at 8:05 p.m.
Respectfully
submitted,
________________________,2007 __________________________
William
G. Syfert, Chairman
________________________,2007 __________________________
Lawrence
Hawkins III Secretary